Contracts & Commercial Law

India's Contract Management Knowledge Hub

Claims management, variation orders, force majeure, and Indian contract law — verified from the Indian Contract Act, FIDIC, GCC, and 15+ years of commercial practice.

Browse by Contract Topic

Claims Management

Extension of Time, delay damages, variation orders, and claims administration.

Force Majeure

Excusable delays, COVID precedents, and regulatory change provisions.

Contract Drafting

Key clauses, boilerplate, payment terms, and the Indian Contract Act 1872.

Dispute Resolution

Arbitration, adjudication, mediation, and dispute boards under Indian law.

Government Contracts

GCC, CPWD, NIT conditions, and government procurement obligations.

EPC & Construction

EPC contracts, milestone payments, LD clauses, and FIDIC in India.

Contract Guides

Expert Guides on Contract Management

Practical, verified guidance written from the Indian Contract Act, FIDIC, GCC, and official government sources.

Claims Management

Claims for Extension of Time under FIDIC: A Practical Guide

Under review — publishing soon.

Force Majeure

Force Majeure in Indian Construction Contracts: 2024 Analysis

Under review — publishing soon.

Claims Management

Variation Orders: Managing Contract Changes Under GCC

Under review — publishing soon.

Contract Drafting

Liquidated Damages vs Penalty: Understanding Indian Contract Law

Under review — publishing soon.

EPC & Construction

Notice Requirements in EPC Contracts: A Practical Guide

Under review — publishing soon.

Contract Drafting

Contract Termination for Convenience: Rights and Remedies in India

Under review — publishing soon.

Professional Templates

Ready-to-use Contract Templates

Professionally drafted documents built from real commercial and claims practice — save time on the documents that matter most.

Contracts

EOT Claim Notice

Extension of Time claim letter under FIDIC or GCC contracts.

Template in preparation.

Contracts

Force Majeure Notice

Force majeure event notification and relief claim letter.

Template in preparation.

Contracts

Variation Order

Contract change order documentation with valuation methodology.

Template in preparation.

AI-Powered Tools

AI Clause Explainer — Powered by Claude (Anthropic)

Paste any contract clause. Get a plain-English explanation, key obligations for each party, and risk flags — grounded in HaritaZen's verified knowledge base. Not a generic chatbot.

AI Draft — review before use. Powered by Claude (Anthropic). Not legal advice.

Contract Calculators

Calculate it in seconds

Time and money calculators for claims management and contract administration.

Extension of Time Calculator

Calculate justifiable EOT days under FIDIC or GCC contracts.

Calculator in development.

Liquidated Damages Calculator

LD amount for project delays, per your contract formula.

Calculator in development.

Escalation Calculator

Price variation under CPWD or government contract escalation formula.

Calculator in development.

Contract Management — Frequently Asked Questions

What is the Indian Contract Act 1872 and what contracts does it govern?

The Indian Contract Act 1872 is the primary legislation governing contracts in India. It governs all agreements involving offer, acceptance, consideration, capacity, and free consent. Construction contracts, EPC agreements, supply contracts, and service contracts in India are all subject to this Act, along with any sector-specific provisions under CPWD/GCC or FIDIC when applicable.

What is force majeure in Indian construction contracts?

Force majeure is a contractual clause that excuses a party from performance when an extraordinary event beyond their control makes performance impossible or impractical. Under Indian law, force majeure provisions must be explicit in the contract — Section 56 of the Indian Contract Act (frustration) provides limited residual relief. Typical events include natural disasters, pandemics, riots, and regulatory government action. COVID-19 was treated as a force majeure event by many Indian courts and government authorities.

How do I make a valid Extension of Time (EOT) claim under FIDIC or GCC contracts?

A valid EOT claim requires: (1) a qualifying event — typically defined in the contract, such as force majeure, employer-caused delay, or statutory variation; (2) timely notice — FIDIC Sub-Clause 20.1 requires notice within 28 days, GCC Clause 5 typically requires 14 days; (3) contemporaneous records — daily site diaries, correspondence, and site instructions; and (4) a substantiated claim demonstrating the causal link between the event and the delay. Late notice can bar the claim entirely under strict FIDIC interpretation.

What is the difference between Liquidated Damages and penalty in Indian contracts?

Under Section 74 of the Indian Contract Act 1872, Indian courts treat LD and penalty as a single category — courts may award a reasonable amount even if the contract specifies a fixed LD rate. Unlike English law, Indian law allows courts to reduce an unreasonably high LD rate to "reasonable compensation." However, if the LD rate is a genuine pre-estimate of loss, courts typically enforce it. Contractors can challenge an LD deduction if the employer caused or contributed to the delay.

When can a contract be terminated for convenience under Indian law?

Most Indian government contracts (GCC, CPWD) and FIDIC contracts include a termination for convenience clause, allowing the employer to terminate without a breach by the contractor. Under GCC, compensation typically covers work completed plus certified costs — not lost profit on unexecuted work. Under FIDIC Red Book Clause 15.5, the employer must pay for work executed, plant and materials, reasonable profit on future work, and demobilisation costs. Without an express termination for convenience clause, termination must be for breach or frustration.

What is the limitation period for contract disputes in India?

Under the Limitation Act 1963, the general limitation period for contract disputes in Indian courts is 3 years from the date the cause of action arises. The same period applies to arbitration proceedings under the Arbitration and Conciliation Act 1996 (Section 43 applies the Limitation Act to arbitrations). A written acknowledgement of liability or a part-payment can reset the limitation clock. Missing the limitation period bars the remedy entirely, even if the underlying claim is valid.

Build your contract management expertise

Guides, templates, and AI tools — all grounded in verified knowledge and built for Indian commercial practice.